[The following information applies to the questions displayed below.]
| Fogerty Company makes two products, titanium Hubs and Sprockets. Data regarding the two products follow: |
| | Direct Labor-Hours per unit | Annual Production |
| Hubs | 0.80 | 19,000 units |
| Sprockets | 0.40 | 78,000 units |
| | ||
| Additional information about the company follows: |
| a. Hubs require $17 in direct materials per unit, and Sprockets require $11. |
| b. The direct labor wage rate is $15 per hour. |
| c. Hubs are more complex to manufacture than Sprockets and they require special equipment. |
| d. The ABC system has the following activity cost pools: |
| | | Estimated Overhead | | Activity | | |
| Activity Cost Pool | Activity Measure | Cost | Hubs | Sprockets | Total | |
| Machine setups | Number of setups | $ | 24,000 | 95 | 94 | 189 |
| Special processing | Machine-hours | $ | 170,000 | 4,100 | 1 | 4,101 |
| General factory | Direct labor-hours | $ | 271,000 | 15,200 | 31,200 | 46,400 |
| | ||||||
6.
value:
1 points
1 points
| Requirement 1: |
| Compute the activity rate (i.e., predetermined overhead rate) for each activity cost pool. (Do not round intermediate calculation. Round your final answers to 2 decimal places. Omit the "$" sign in your response.) |
| Activity Cost Pool | Activity Rate | |
| Machine setups | $ | per setup |
| Special processing | $ | per MH |
| General factory | $ | per DLH |
| | ||
| Worksheet | Learning Objective: 03-2 | |
| Difficulty: Basic | Learning Objective: 03-3 | |
7.
value:
1 points
1 points
| Requirement 2: |
| Determine the unit product cost of each product according to the ABC system. (Do not round intermediate calculation. Round your final answers to 2 decimal places. Omit the "$" sign in your response.) |
| Unit product cost of Hubs | $ |
| Unit product cost of Sprockets | $ |
| Worksheet | Learning Objective: 03-2 | |
| Difficulty: Basic | Learning Objective: 03-3 | |